Pave Aways offer an extensive range of experience across a spectrum of construction projects.
Education


Location – Cuddington Primary School, Northwich, Cheshire CW8 2NY
Value
– Up to £250,000
Duration – 16 weeks
Completion – November 2015
Architect – TACP Architects
Engineer – Patrick Parsons Ltd
Form of Contract – JCT Intermediate Contract 2011
Client – Cheshire West & Chester Council

The project comprised the part demolition of a group room and construction of a single storey Classroom extension and a single storey Group Room extension. Associated work includes a minor playground extension and a drainage diversion

The extension was fromed from masonry walls, flat roof sinlgle ply membrane and new curtain walling / winodws and doors.

The works were challenging as the extension attached onto the school corridor which remained in operation during the full works.